Chevron Philippines Inc.
2020 Project
• Total Plant Maintenance (Five Terminals)
March 2020 - Up to Present
• Tank Repairs
• Installation and Dismantling (Scaffold Rental)
• Equipment Rentals
2019 Project
• Terminal Automation System Phase I (Special Project)
• UXO Detection and Retrieval
• Tank 73 Cleaning and Blasting
• Tank 3 Cleaning
• Modification and Replacement of EFR Tank Seal of Tank 74
• Golf Course Rehabilitation
• Demolition of Old Oil Wharf Field Office
• Repair of Fenders
• Repair of Catwalk underdeck of Berth 5 and 6
• Rerouting and Crane Use
• Repair at Oil Wharf
• Fabrication of 60 trash bins for BT/BTF and Banaba Housing Compund
2018 Project
• Improvement of Manifold Drainage at Chevron Bats
• Demolition/Disposal of Waste Phase 2
• Supply of Manpower, tools and equipment for the erection of scaffold for Air Winch Repair
• Supply of Manpower and Materials needed for the repair and repaint of RCMAs Oil Wharf berth 5
• Supply of Manpower, Tools and equipment for the repair of catwalk underdeck of berth 2 & 3
• Erection of scaffold at Slop tanks and De Ballast water tanks at Oil Wharf Berth 5A/5/6.
• Convan Power Supply at Batangas Terminal
• Supply of Manpower, Tools and equipment for the Fabrication and Modification of OWS Ladder
• Oil Wharf Pipeline Painting Project for Berth 5A