Goro Nickel
The Goro Nickel Project was constructing a mine and integrated processing plant in New Caledonia. CJI under Cape East provides manpower resource, equipment supply and technical supervision for the fabrication of FRP Pipe Spools. The Fabrication Area is located at AG&P Module Yard in Bauan Batangas and these fabricated pipe spools are to be installed on the modules as preparation for tie-up in New Caledonia. EPC Contractor was Foster Wheeler.
REPAIR OF VESSELS
The repair of FRP Vessels was undertaken as a variation work for the FRP Pipe Spool Fabrication in order to conform to the QA/QC standards.
INSTALLATION OF VALVES AND FITTINGS
CJI under Cape East provides manpower resources equipment supply and technical supervision for the installation of valves and fittings in the Module Area